Waterloo Wind Farm

The Waterloo Wind Farm is located 120kms North of Adelaide, South Australia. CATCON were contracted to design & construct 37 V90 Turbine footings, hardstands, roads, sub-station and control buildings. The terrain comprised of steep and narrow ridges and rock strata which required blasting and a host of machinery including; D9 Dozers, 80t Excavator, 30tn Excavators, […]

Continue reading

Lake Bonney Wind Farm – Stage 2

The construction of the civil and electrical works associated with the Lake Bonney Stage 2 Wind Farm, on a site 11km long and 1 km wide with 53 wind turbines, was a Joint Venture between CATCON with Areva. Lake Bonney represents our firm’s milestone involvement on a large scale wind power resource energy project. 350m3 […]