Waterloo Wind Farm

The Waterloo Wind Farm is located 120kms North of Adelaide, South Australia. CATCON were contracted to design & construct 37 V90 Turbine footings, hardstands, roads, sub-station and control buildings.

The terrain comprised of steep and narrow ridges and rock strata which required blasting and a host of machinery including; D9 Dozers, 80t Excavator, 30tn Excavators, 30tn Dump Trucks, 50tn Cranes, Rocksaw and 100tn cranes.

Facts & Figures:

  • 37 Towers
  • 13,000m3 of concrete Used
  • 18km of road
  • In excess of 300,000tn of material moved
Posted in Wind.