Lake Bonney Wind Farm
Layout Main Left
Lake Bonney Wind Farm

The construction of the civil and electrical works associated with the Lake Bonney Stage 2 Wind Farm, on a site 11km long and 1 km wide with 53 wind turbines, was a Joint Venture between CATCON with Areva. Lake Bonney represents our firm’s milestone involvement on a large scale wind power resource energy project.

350m3 of concrete is provided to each turbine tower footing. The towers are 4.2 metres in diameter at the base, 78 metres high and support the 90 metre diameter tri-propellors. Each turbine generates a capacity of 3MW of energy.

Existing limestone excavated material was recycled in use for the preparation of new road bases. Our firm’s civil works involvement includes design and construction of all concrete works, particularly the major footings to the wind turbines, substantial road works and all underground electrical Services.

Lake Bonney Wind Farm – Stage 2 is an environmentally significant development in the experience and growth of CATCON.

Gallery

Lake Bonney Bulldozer Pouring the Foundations Finished Foundations
Lake Bonney Trenching Lake Bonney Substation Lake Bonney Finished Turbine

pdf Download PDF Fact Sheet

>>Back to Major Infrastructure

Layout Main Right   Layout Right Left
Other Projects

Pelican Point

Tallawarra

Torrens Island

Mawson Lakes

Layout Right Right
Layout Bottom Left
News

28 Jun 2010 >> CATCON Career Opportunities >> CATCON have been successful in securing new projects and are now hiring. Click he ... [more]

27 Nov 2009 >> Collgar Wind Farm >> CATCON is proud to announce the succesful tender for an EPC civil contract from Vestas for the Collg ... [more]

11 Nov 2009 >> [Careers] New Position Available >> A position description for Project Engineer has been added to the careers section ... [more]

17 Sep 2009 >> [Update] New Project Added >> The Blakes Crossing sub-division project has been added. Click ... [more]

Layout Bottom Right